There will be some dates where construction activities will extend beyond 6pm:
- Concrete Activities: 14-Apr, 5-May, 9-Jun, 23-Jun, 21-Jul
- Spray Foam Activities: 4-May through 22-May
- Note: These dates may change. Check back here for updates:
- 22-Apr: The 6-May concrete pour moved up 1 day to 5-May
Read the Letter to Abutters regarding this temporary change in hours. (27-Mar-2020)
Please visit the 129 Parker project page for more information.