DPW: 2021 Paving Projects

The Town of Maynard is pleased to announce our 2021 Approved Roadway Paving Projects. The following Public Roadways will undergo a replacement with a tentative start date of May 17, 2021 (weather dependent). Roadway paving will be conducted by Sunshine Paving, and their sub-contractors. Estimated project completion 10-14 days.

Nason Street – #12 to #42 (water main failure Winter 2020)
            Process: Mill and Overlay

Brooks Street – Concord Street to Jethro Street
            Process: Reclamation

Brooks Street – Summer Street to Concord Street
            Process: Reclamation

Durant Avenue – Dana Road to Cul-de-sac
            Process: Reclamation