Category Archives: DPW

Roadway Construction Notices

Roadway construction began the week of October 15, 2018. Construction activities include excavation, sewer pipe installation, manhole repair and roadway paving. The Town of Maynard has contracted with N. Granese & Sons, Inc to complete the roadway and sewer construction services.

UPDATE: 22-Apr-2019: Please be advised, the 129 Parker Street Downstream Sewer Project is progressing and construction will conclude on Powder Mill Road by May 3rd. Project construction will begin on Waltham Street beginning on May 6th for three weeks. Powder Mill and Waltham Streets are scheduled to be repaved during the Summer of 2019.

If you have any questions please contact the Maynard DPW at 978-897-1317 or DPW@townofmaynard.net.

DPW: Summer Street Sidewalk Construction resumes Mar 28th

The Summer Street sidewalk construction project is scheduled to resume on or about March 28th, 2019. Construction activities include excavation, sidewalk construction, curb installation, walkway/driveway restoration and roadway paving. The Town of Maynard has contracted with Detour Construction LLC to complete the construction services.

Locations are as follows:

  • Summer Street – Brooks Street to Apple Ridge Road

Once construction is started, no on-street parking will be allowed until all construction activities are completed in the area.

Homeowners on the affected roadway may temporarily not be able to access their driveway with vehicles when crews are excavating and pouring sidewalks directly adjacent to the property. Homeowners will be notified 24 hours in advance of driveway access interruption via a flyer that will be distributed individually.

Individual driveway work may take 2-3 days to complete at each location. Temporary walkways will be installed over the new sidewalk while it cures to allow for pedestrian access to each property during construction. We apologize for any inconvenience.

Construction will start at Patti Lane on March 28th, and will continue through the above listed streets. Construction is scheduled to continue through April, weather permitting.

If you have any questions please contact the Maynard Department of Public Works at 978-897-1317 or DPW@townofmaynard.net.